Steps
- Open Production → Planning (MRP); under «Run MRP» set «Horizon (days)» (30 by default) and press «Run planning».
- The plan counts open sales orders in the horizon, accepted quotations, components of open production orders and reorder points, minus stock and open purchase and production orders.
- Read the results: each line is Make or Buy with the quantity, «Needed by», «Why» and the supplier and price; untick the lines you do not want.
- Choose «Supplier for lines without one» when buy lines show no supplier yet, then press «Create draft orders».
- Make lines become draft production orders and buy lines one draft purchase order per supplier; open them from the → links, adjust them and send them.
Tips
- Quantities cannot be changed on the plan; edit the draft orders.
- Buying lines also need the purchasing right.