Steps
- On the job, open Variations and draft a variation order with its lines; mark it sent and share the approval link, or record the client's written approval.
- Open Payment applications and create one: every contract line (approved variations included) starts at the % certified last time.
- Enter the % or quantity done to date per line and save; retention, advance recovery and earlier certificates are taken off.
- Submit it to the client, then record the certificate (who certified it and the reference).
- Create the invoice for the certified amount; at practical completion and at the end of the defects period release the retention the same way.